Sand And Cement Screed Calculator Estimate

Screed Calculation Formulas:

\[ \text{Cement (kg)} = \left[\text{Area (m²)} \times \text{Thickness (m)} \times 1.33 \times \left(\frac{1}{1 + \text{ratio}}\right)\right] \times 1440 \] \[ \text{Sand (kg)} = \left[\text{Area (m²)} \times \text{Thickness (m)} \times 1.33 \times \left(\frac{\text{ratio}}{1 + \text{ratio}}\right)\right] \times 1600 \]

meters
(e.g., 1:3 = 3)

Unit Converter ▲

Unit Converter ▼

From: To:

1. What is Screed?

Screed is a thin layer of cement and sand mixture applied to a concrete floor base to create a smooth, level surface for final floor coverings. The correct ratio of cement to sand is crucial for strength and workability.

2. How Does the Calculator Work?

The calculator uses these formulas:

\[ \text{Cement (kg)} = \left[\text{Area} \times \text{Thickness} \times 1.33 \times \left(\frac{1}{1 + \text{ratio}}\right)\right] \times 1440 \] \[ \text{Sand (kg)} = \left[\text{Area} \times \text{Thickness} \times 1.33 \times \left(\frac{\text{ratio}}{1 + \text{ratio}}\right)\right] \times 1600 \]

Where:

3. Importance of Accurate Calculation

Details: Proper calculation ensures you purchase the right quantities of materials, avoiding costly over-ordering or inconvenient shortages during the project.

4. Using the Calculator

Tips: Measure your area accurately in square meters. Common screed thickness ranges from 50mm to 100mm (0.05m to 0.1m). Typical ratios are 1:3 to 1:5 cement:sand.

5. Frequently Asked Questions (FAQ)

Q1: What's a typical cement:sand ratio for screed?
A: For floor screeds, 1:3 to 1:4.5 is common (1 part cement to 3-4.5 parts sand by volume).

Q2: How much water should I add?
A: Enough to achieve a workable consistency - about 20-25% of the cement weight, but adjust based on sand moisture.

Q3: What if my area isn't rectangular?
A: Break it into rectangular sections, calculate each separately, then sum the results.

Q4: Should I order extra material?
A: It's wise to add 5-10% to account for spillage, uneven surfaces, and calculation margins.

Q5: How long does screed take to dry?
A: Typically 1 day per mm for the first 50mm, then longer for thicker applications (about 4-6 weeks for full curing).